Weekend Activity Monitor

Annual Alternative Site Recovery Test
Important Updates: 

Alternative Site Recovery Test - Saturday 5 February 2022

NOTE: Please refresh this page, the Weekend Activity Monitor (WAM)  will not automatically update.

Please note that all times below are indicative and subject to change.  Any changes to the schedule will be updated on the WAM.

LSE and TRADEcho ASR Guide 

Turquoise ASR Guide  

Schedule Task Status Start End Note
Saturday, February 5, 2022 - 07:00 Start of Day - Connectivity to all Millennium Exchange gateways at PDC Completed 07:00 Millennium Exchange (LSE and Turquoise) Group Ticker Plant TRADEcho
Saturday, February 5, 2022 - 07:00 LSE - Pre-Trading Completed 07:00 07:05 Pre-Trading
Saturday, February 5, 2022 - 07:15 TRADEcho - Connectivity and Trade Reporting at PDC Completed 07:15 08:25
Saturday, February 5, 2022 - 07:50 LSE - Open Auction Call Completed 07:50 08:00 Orders injected
Saturday, February 5, 2022 - 08:00 LSE & Turquoise (UK and EU) - Regular Trading Completed 08:00 08:30 Orders Injected to generate trades and trade reports published.
Saturday, February 5, 2022 - 08:30 All Systems - Simulated Failure at PDC Completed 08:30 Millennium Exchange (LSE and Turquoise) Group Ticker Plant TRADEcho
Saturday, February 5, 2022 - 10:00 TRADEcho - Connectivity and Trade Reporting available in SDC Completed 10:00 12:00
Saturday, February 5, 2022 - 10:00 LSE & Turquoise (UK and EU) - Customer Connectivity Reestablished Completed 10:00 Connectivity available for LSE, Turquoise (UK & EU) at SDC. Native Trading 05 and 06 will not be available for Turquoise at SDC,
Saturday, February 5, 2022 - 10:00 LSE - Market Restart Completed 10:00
Saturday, February 5, 2022 - 10:20 LSE - Resume Market Auction Call Completed 10:20 10:30
Saturday, February 5, 2022 - 10:30 LSE & Turquoise (UK and EU) - Re-commence Regular Trading and intraday reference data action performed by London Stock Exchange Completed 10:30 12:00
Saturday, February 5, 2022 - 13:30 LSE & Turquoise (UK and EU) - Market Close Completed 13:30
Saturday, February 5, 2022 - 13:30 All Markets - End of ASR Completed 13:30 Please contact the Technical Account Management team (londonTAM@lseg.com) to signoff your testing.
Saturday, February 5, 2022 - 13:30 Turquoise (UK and EU) - Market Close Completed 13:30
Saturday, February 5, 2022 - 14:00 All Markets - Roll back to PDC Completed 14:00 McPoll and Unicom service will be enabled for customers to test connectivity back to PDC